Hills Road cycleway this weekend

Red tarmac going down

Red tarmac going down

Hills Road cycleway update: The County Council have advised me that their contractors will be laying down the final stretch of tarmac on the new cycleway Hills Road this Sunday — between Glebe Road and the end of the cycleway near Queen Edith’s Way and Long Road.

A reminder that there is still time to comment on the proposals for cycleways on Queen Edith’s Way and for the Fendon Road roundabout – until 1st August.

Hills Road cycle lanes: Frequently Asked Questions

Hills Road cycle lanesCambridgeshire County Council’s new cycle lanes on Hills Road have generated a record number of questions and concerns. Here are some of the most common ones:

Q: Why is Cambridgeshire County Council doing this?

A: The County wishes to enhance cycleways in order to meet the needs of the rapidly growing population, which will result in more traffic. The County would like to keep the extra motorised traffic to a minimum and encourage other modes of transport. Similar schemes have substantially increased cycling in other areas, particularly amongst children.

Q: How is it being funded?

A: Through central government’s Cycle City Ambition Fund.

Q: Who approved it?

A: County Council Highways officers identified Hills and Huntingdon Roads as main routes into Cambridge that would benefit from enhancement. The scheme was first presented to Cambridgeshire County Council’s Economy and Environment Committee in May 2014. Councillors deferred it as they were unhappy with elements of the scheme including the floating bus stops, and changes were made. It was passed in July 2014 at the second time of asking, with an undertaking to conduct traffic surveys before and after implementation, an amendment I requested, in order to assess the level of rat-running as a result of the narrower road carriageway. One survey was done last year and another will be done after completion.

Q: Will any trees be felled?
A: The County Council has stated categorically that no trees will be felled. Some pruning of vegetation that encroaches onto the public highway may be necessary.

Q: Will new rubbish bins be provided at bus stops?
A: Providing litter bins is a City Council responsibility. The County Project Team is discussing with City Council about replacement of old bins with new ones and other locations where a new bin may be desirable.

IMAG1839Q: How will works across junction mouths be organised?
A: Junctions are being closed off at weekends to allow works to be safely and quickly undertaken. Letterdrops to residents and advanced warning notices inform those affected at least one week in advance.

Q: How will work on junction mouths of cul de sacs be organised?
A: Junction works to be constructed one half at a time with access maintained into/out of the cul de sac.

Q: Could the concrete layby near Glebe Road be used as a bus stop?
A: This layby is halfway between two other bus stops so if a bus stop went there, the other two stops would be removed, meaning bus users would have a long walk to the next stop.

Q: What consultation took place before this scheme was agreed?
A: The proposals were advertised in FOCUS, as well as via a streetletter from myself to all residents in Hills Road and several of the side roads. The County Council delivered leaflets with feedback forms to a wide local area and held local staffed events in March 2014. Drawings and information on the proposed scheme were put on the County Council website, together with contact details.  The Team also had information stalls at Hills Road VI Form College, Long Road VI Form College and at an Addenbrooke’s Sustainability Event.

In November 2014 the County Cycling Team wrote again to residents inviting them to a pre-construction event at Rock Road Library — an opportunity to find out about boundary issues, construction sequence etc.  This event was well attended by residents of Hills Road. The letter included details of where the final drawings could be seen on the website and asked residents to provide email addresses if they wanted updates on the scheme.

Q: What will happen when there are weddings and funerals at the church? What about hearses and wedding cars?
A: The Cycling Team has been liaising with St John’s Church. During construction, the cycleway works will be left in an appropriate state to accommodate wedding cars and hearses. After completion, wedding cars and hearses will be able to park for the duration of services, as the new cycle lanes are not ‘mandatory’ and there are no loading restrictions attached to the double yellow lines.

Q: Is the width of the carriageway being reduced?
A: Yes, the carriageway width is being reduced, to 6m.

Q: Will there be a loss of grass verges?
A: The roadside verges next to the road will go, but there is a half metre sedum strip between the cycleway and the footway on both sides of the road.

On the outbound side of Hills Road, the verges next to the houses will be largely the same except where space is needed for the floating bus stops.   On the citybound side (the side with the current shared-use cycle/footway) the verges next to the houses are increasing.

Here is a link to the drawings showing details:
On the west side of Hills Road (S to N), from No. 284 to 256, and from 248 to 228, a 800 or 900mm wide strip of footway will be turned into new verge. From No. 226 to Homerton College this strip widens to between 1.4 and 1.6m and then it is about 2.5m wide running past Homerton College. On the east side (S to N),  there are no significant areas of new verge until you get to the block north of Glebe Road, No.s 253 to 247 have 1.2m wide new verges. Re. the loss of those verges on the residence side of the footway, the only real areas where there is loss of verge is near the floating bus stops (and to some extent near crossings) but this does vary depending on the location.

Q: Was Cambridge City Council consulted?
A: The City Council is a statutory consultee for every cycling project within Cambridge.   The Project Team was keen to gain the input of City’s Urban Design team on the Huntingdon Road and Hills Road schemes – a meeting with the City’s Head of Urban Design was arranged before the schemes were approved and, in neither case were concerns raised about the proposals.

Q: Are our streetlights being replaced to facilitate the cycleway scheme?
A: No, the streetlighting on Hills Road is not being replaced as a result of the cycleway scheme but as part of the County’s streetlighting replacement programme – as such, the lighting along the whole length of Hills Road is being updated to conform with new British standards.

Q: At present, the pavement cycleway on the northbound side of Hills Road provides a convenient way of turning into Luard Road. Won’t the new arrangement be more dangerous?
A: The main carriageway on Hills Road will be narrowed to 6m, which should reduce traffic speeds. Equally, the speeds of vehicles exiting side roads should be slowed by the tighter turning movements required by the new scheme.

The Road Safety Audit 2 did not raise any issues about the changes to this junction, nor the removal of the shared-use foot/cycleway. The new scheme (unlike the shared-use foot/cycleway) gives cyclists on Hills Road priority through the junction with Luard Road so there should be a reduction in the number of cycle-related accidents at this location. Less confident cyclists on Hills Road may choose to pull in and wait on the left side of the new southbound 2.3m cycle lane before turning right. The County Council will monitor the situation and may consider installing a central island that would offer cyclists some protection whilst waiting to turn right.

Q: How will it be made clear that vehicles cannot drive across or park on the cycleway?

A: Cycle symbols will be added to the cycle lane and double yellow lines will be painted on the main carriageway (next to the outside edge of the cycle lane) to prevent parking in the new lane. This work should be taking place on the northbound side in  November 2015.

Q: How will the construction for the southbound side of Hills Road be handled?

A: The intention is to keep the citybound shared-use path open whilst the outbound works are carried out – to ensure safety for cyclists and pedestrians during the construction phase. The footpath work will be done first, then the cycleway and ‘Cambridge kerb’.

Q: Whom do I contact for more information?
A: If it is an operational matter, contact Grant Weller at Cambridgeshire County Council: [email protected] If your question is about consultation or general principles, contact Mike Davies: [email protected]

MONDAY 5TH OCTOBER: REPORT ON THE PRESENTATION ON CYCLING SCHEMES AT SOUTH AREA MEETING, ST JOHN’S CHURCH, HILLS ROAD.

Cambridge South Area: streetlighting Q&A plus new layout for Cherry Hinton High Street

The next South Area meeting is at St John’s Church Hills Road on Monday 30th March and here is the agenda.

The County Council’s streetlighting contractor Balfour Beatty will be sending a representative to explain the lighting contract, and answer questions about replacements in Queen Edith’s.

There will be reports on changes to the road layout in Cherry Hinton and Hills Road, and environmental services activity. Finally, the committee will vote on grants to community groups.

The meeting is open to the public and there is a slot at the beginning of the meeting to ask questions of councillors. Sometimes questions can be answered on the spot, and if questions highlight issues that need to be addressed, they will be taken up by councillors after the meeting.

Floating bus stops, what do you think?

floatingbusstopHills Road is to benefit from over a million pounds of government funding for a new road layout that aims to improve conditions for pedestrians, bus users and cyclists. There is a plan for segregated cycle lanes in three of the main roads into the city: Hills Road, Trumpington Road and Huntingdon Road.

An innovative feature of the scheme will be ‘floating bus stops’, which have proved successful in Brighton and London. This will avoid the danger of cyclists overtaking buses at stops, but it will be important to make sure it is safe for bus passengers.

The County Council is running a consultation begins next week, with exhibitions and events at various local centres. There has already been one at St John’s Church and there are more at Addenbrooke’s (Friday March 14th, 11.00am-2pm) and the Perse School ( Wednesday March 26th, 6,30-8.30pm).

For full details, see http://www.cambridgeshire.gov.uk/CMSWebsite/Apps/News/Details.aspx?ref=1330

The meeting will also include a presentation from the neighbourhood police and planning applications, including one for flats in Queen Edith’s Way – yes, more flats.

The meeting begins at 7pm, with an Open Forum, at which anyone can ask questions or make statements.

Advice surgery this Saturday

I’ll be at the St James’s Church coffee morning this Saturday doing an informal advice surgery from 10.30 to 11.30am. If you have any questions about the area or problems that need sorting out, or good ideas to improve the areas, please drop in and say hallo. If I can’t give you an answer right away, I’ll do my best to find out.

ADVICE SURGERY ST JAMES’ CHURCH WULFSTAN WAY 10.30-11.30am SATURDAY 11th JANUARY 2014